691.6 MW Natural Gas operating in Maricopa, AZ
691.6 MW
Nameplate Capacity
3
Generators
units
Natural Gas Fired Combined Cycle
Technology
2003
Operating Since
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Plant reference point
33.3405, -112.8634
Reference point calculated from the selected footprint.
Mapped site outline
Site outline mapped in OpenStreetMap. It is not a surveyed or legal boundary.
This mapped site is shared by multiple plant records.
County
Maricopa, AZ
Nearby Plants
The route starts at a transmission substation on the mapped site; its link to the plant’s generation equipment is unconfirmed.
3 mapped line sections connect the two facilities over 6.624 km. The line reaches both facility footprints in the source data.
The actual electrical circuit, the official point of interconnection (POI), and the market settlement node require separate evidence.
Source checked 26 Oct 2026. Facility colors and shapes indicate source-reported function, not ownership or a confirmed plant connection.
This release uses a national source capture. Coverage and electrical detail vary by location; missing map data does not mean there is no connection. Lettered substation names are display labels where the source has no name. They do not identify ownership or function.
Source snapshot: 25 Oct 2026.
Reverse views of the same physical route are grouped in the route selector. All source records are retained.
Method: source-node-path-v2 · Release: gcr-73c6ce9c596ada3ec63d5523
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Salt River Project | Salt River Project | — |
| Owner(s) | Salt River Project | Salt River Project | — |
| Status | Operating | — | — |
Summary generated Mar 21, 2026 (UTC).
Source dates used by this summary were not recorded.
These may postdate the saved summary; they do not establish which inputs it used.
Mesquite Generating Station Block 1 is a 691.6 MW natural gas-fired combined cycle power plant located in Maricopa County, Arizona. The plant began operating in 2003 and is owned and operated by Salt River Project (SRP). It consists of three generators. The plant is located within the Western Electricity Coordinating Council (WECC) NERC region and is under the balancing authority of SRP.
In the most recent year with available data, Mesquite Generating Station Block 1 produced 3,522,461 MWh of electricity, achieving a capacity factor of 58.2%. The plant ranks as the 13th largest in Arizona out of 26 plants, and 322nd nationally out of 945 plants.
Grid Region
Mountain West
Market
WEIM Participant
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
Salt River Project (SRP)
Grid Voltage
500.0 kV
Regulatory Status
RE — Regulated
Entity Type
Political Subdivision
Sector
Electric Utility
Connection evidence
Mapped route candidate
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
356.7K MWh
Latest Month
3.5M MWh
Annual Generation
58.2%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2013
$965/kW
Est. Construction Cost
Total estimated cost: $667.5M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
This plant's balancing authority participates in CAISO's Western Energy Imbalance Market (WEIM). Direct nodal pricing data is not yet available.
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
Last updated 2026-07-11
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this asset.