Search plants, projects, owners, and states
35 MW Wind operating in Bremer, IA
35 MW
Nameplate Capacity
1
Generators
unit
Onshore Wind Turbine
Technology
2012
Operating Since
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Greenbacker Renewable Energy Corporation | Greenbacker Renewable Energy | — |
| Owner(s) | RPG Elk/Hawkeye Investco, LLC, RPMA Wind Holding II | Greenbacker Renewable Energy | — |
| Status | Operating | retired | — |
GEM identifies the owner as Greenbacker Renewable Energy
This entity is not yet in the GEM ownership database — chain unavailable.
Hawkeye Wind Farm is a 35 MW wind power facility located in Bremer County, Iowa. The plant began operating in 2012 and is owned and operated by Greenbacker Renewable Energy Corporation. It utilizes a single generator consisting of onshore wind turbine technology. The facility ranks 77th out of 122 wind plants in Iowa and 995th nationally out of 1424.
The wind farm's turbines have a hub height of 100 meters and a rotor diameter of 127 meters. The turbines were manufactured by GE Wind and are model GE2.5-127. In its most recent year of operation, Hawkeye Wind Farm generated 173,276 MWh of electricity, achieving a capacity factor of 56.5%. The plant operates within the Midcontinent Independent Transmission System Operator, Inc. (MISO) balancing authority and the MRO NERC region.
Generated from EIA, GEM, and public data sources
ISO/RTO
MISO
Market
ISO/RTO Member
NERC Region
MRO — Midwest Reliability Organization
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc.. (MISO)
Grid Voltage
69.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
14.3K MWh
Latest Month
173.3K MWh
Annual Generation
56.5%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2013
$1,895/kW
Est. Construction Cost
Total estimated cost: $66.3M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
Bethel Substation · 69 kV
Substation Distance
3.721 km
Operator
ITC
Coord Source
OSM spatial
Market Position
ISO/RTO Market
MISO
LMP Node
ALTW.HAWKEYE1
Pricing Hub
MINN.HUB
Location Type
Generation Node
Node Source
Curated node match
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
No insights linked yet for this plant.
Insights enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No Ask reports yet for this entity.
Ask about Hawkeye Wind FarmForward forecasts, scenario decomposition, and risk-decision tooling for this asset.