54 MW Hydro operating in Burnet, TX
54 MW
Nameplate Capacity
2
Generators
units
Conventional Hydroelectric
Technology
1951
Operating Since
Coordinates
30.5560, -98.3384
County
Burnet, TX
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Lower Colorado River Authority | Lower Colorado River Authority | — |
| Owner(s) | Lower Colorado River Authority | Lower Colorado River Authority | — |
| Status | Operating | operating | — |
Wirtz Dam was constructed from 1949 to 1951 to provide hydroelectric power and to form Lake Lyndon B. Johnson, one of the Texas Highland Lakes. Lake LBJ ‒ as it is more commonly referred to ‒ provides cooling water for the Lower Colorado River Authority's Thomas C. Ferguson Power Plant along Horseshoe Bay.
Read more on WikipediaThe Granite Shoals hydroelectric plant is located in Burnet County, Texas. The plant has a total capacity of 54 MW across two generators and is owned and operated by the Lower Colorado River Authority. It began operating in 1951, utilizing conventional hydroelectric technology and water as its primary fuel source.
In the most recent year of available data, Granite Shoals generated 22,369 MWh of electricity, resulting in a capacity factor of 4.7%. The plant operates within the Electric Reliability Council of Texas (ERCOT) balancing authority and the TRE NERC region. Granite Shoals ranks as the 6th largest hydroelectric plant out of 24 in Texas, and 290th out of 1464 nationally.
Generated from EIA, GEM, and public data sources
ISO/RTO
ERCOT
Market
ISO/RTO Member
NERC Region
TRE — Texas Reliability Entity
Balancing Authority
Electric Reliability Council of Texas, Inc. (ERCO)
Grid Voltage
138.0 kV
Regulatory Status
RE — Regulated
Entity Type
Political Subdivision
Sector
Electric Utility
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
1.6K MWh
Latest Month
22.4K MWh
Annual Generation
4.7%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2013
$2,294/kW
Est. Construction Cost
Total estimated cost: $123.9M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
Wirtz Substation · 138 kV
Substation Distance
0 km
Operator
Lower Colorado River Authority
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ERCOT
LMP Node
WIR_WIRTZ_G1
Pricing Hub
HB_SOUTH
Alt. Hub / Zone
LZ_SOUTH
Location Type
Resource Node
Node Source
Curated node match
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
No insights linked yet for this plant.
Insights enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No Ask reports yet for this entity.
Ask about Granite ShoalsForward forecasts, scenario decomposition, and risk-decision tooling for this asset.