Briefing/projectactive
Wheelhouse Energy Storage is a 200 MW Battery project in New York, currently active.
NEER Interconnection Holdings, LLC is the reported developer. The reported queue phase is C24. Proposed COD is 2030-12-01.
- Queue ID
- NYISO-C24-205
- Location
- Schoharie, New York
- Technology
- Battery
- Developer
- NEER Interconnection Holdings, LLC
- Market / region
- NYISO
- Point of interconnection
- Edic - Princetown Line #352
What stands out
1
Wheelhouse Energy Storage is a 200 MW Battery project in New York with status active.
2
NEER Interconnection Holdings, LLC is the reported developer.
3
The reported queue phase is C24; proposed COD is 2030-12-01.
Market and operating context
- Queue date
- 2024-09-19
- Proposed COD
- 2030-12-01
- Study phase
- C24
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.