Briefing on Waterloo Solar 1

Entity Briefing
Generated Aug 29, 2026·Dataset freshness not reported
201 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2027-12-01
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Waterloo Solar 1 is a 201 MW Solar+Battery project in Texas, currently active.

Waterloo Solar, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-12-01.

Queue ID
ERCOT-25INR0422
Location
Bastrop, Texas
Technology
Solar+Battery
Developer
Waterloo Solar, LLC
Market / region
ERCOT
Point of interconnection
AUSTROP TO GARFIELD 345kV LINE [Bus # 7040 - 7048]

What stands out

1

Waterloo Solar 1 is a 201 MW Solar+Battery project in Texas with status active.

2

Waterloo Solar, LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2027-12-01.

Market and operating context

Queue date
2023-04-19
Proposed COD
2027-12-01
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Waterloo Solar 1 — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0422
LocationBastrop, Texas
TechnologySolar+Battery
DeveloperWaterloo Solar, LLC
Market / regionERCOT
Point of interconnectionAUSTROP TO GARFIELD 345kV LINE [Bus # 7040 - 7048]
Queue date2023-04-19
Proposed COD2027-12-01