Viento Bravo Wind is a 367 MW Wind project in Texas, currently active.
Webb Wind, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-07-06.
- Queue ID
- ERCOT-28INR0434
- Location
- Jim Hogg, Texas
- Technology
- Wind
- Developer
- Webb Wind, LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345kV 80220 Cenizo - 80079 Cruce Ckt-1
What stands out
1
Viento Bravo Wind is a 367 MW Wind project in Texas with status active.
2
Webb Wind, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2028-07-06.
Market and operating context
- Queue date
- 2025-10-03
- Proposed COD
- 2028-07-06
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters