Query
TYRELL ENERGY STORAGE
Type
Entity Briefing
Entity
TYRELL ENERGY STORAGE
Technology
battery
Generated
2026-10-12T02:50:22.335Z

Briefing on TYRELL ENERGY STORAGE

Entity Briefing
Generated Oct 12, 2026·Dataset freshness not reported
302 MW
Proposed capacity
active
Current status
Battery
Technology
CAISO
Market / region
2032-05-26
Proposed COD
C14
Queue phase
Briefing/projectactive

TYRELL ENERGY STORAGE is a 302 MW Battery project in California, currently active.

The reported queue phase is C14. Proposed COD is 2032-05-26.

Queue ID
CAISO-2125
Location
Orange, California
Technology
Battery
Market / region
CAISO
Point of interconnection
Viejo Substation 230kV

What stands out

1

TYRELL ENERGY STORAGE is a 302 MW Battery project in California with status active.

2

The reported queue phase is C14; proposed COD is 2032-05-26.

Market and operating context

Queue date
2021-04-15
Proposed COD
2032-05-26
IA status
IA Executed
Study phase
C14
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

TYRELL ENERGY STORAGE — verified asset snapshot

FieldValue
Queue IDCAISO-2125
LocationOrange, California
TechnologyBattery
Market / regionCAISO
Point of interconnectionViejo Substation 230kV
Queue date2021-04-15
Proposed COD2032-05-26
IA statusIA Executed