Briefing on Turkey Creek Solar SLF

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
181 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2027-10-26
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Turkey Creek Solar SLF is a 181 MW Solar+Battery project in Texas, currently active.

Greenray Solar Corporation is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-10-26.

Queue ID
ERCOT-25INR0622
Location
Kinney, Texas
Technology
Solar+Battery
Developer
Greenray Solar Corporation
Market / region
ERCOT
Point of interconnection
7425 ODLASW 138kV

What stands out

1

Turkey Creek Solar SLF is a 181 MW Solar+Battery project in Texas with status active.

2

Greenray Solar Corporation is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-10-26.

Market and operating context

Queue date
2024-02-26
Proposed COD
2027-10-26
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Turkey Creek Solar SLF — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0622
LocationKinney, Texas
TechnologySolar+Battery
DeveloperGreenray Solar Corporation
Market / regionERCOT
Point of interconnection7425 ODLASW 138kV
Queue date2024-02-26
Proposed COD2027-10-26