Query
Trelina Energy Storage
Type
Entity Briefing
Entity
Trelina Energy Storage
Technology
battery
Generated
2026-10-11T22:01:36.836Z

Briefing on Trelina Energy Storage

Entity Briefing
Generated Oct 11, 2026·Dataset freshness not reported
120 MW
Proposed capacity
active
Current status
Battery
Technology
NYISO
Market / region
2030-12-01
Proposed COD
C24
Queue phase
Briefing/projectactive

Trelina Energy Storage is a 120 MW Battery project in New York, currently active.

NextEra Energy Resources Interconnection Holdings, LLC is the reported developer. The reported queue phase is C24. Proposed COD is 2030-12-01.

Queue ID
NYISO-C24-207
Location
Seneca, New York
Technology
Battery
Developer
NextEra Energy Resources Interconnection Holdings, LLC
Market / region
NYISO
Point of interconnection
Border City to Station 168 115 kV

What stands out

1

Trelina Energy Storage is a 120 MW Battery project in New York with status active.

2

NextEra Energy Resources Interconnection Holdings, LLC is the reported developer.

3

The reported queue phase is C24; proposed COD is 2030-12-01.

Market and operating context

Queue date
2024-09-19
Proposed COD
2030-12-01
Study phase
C24

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Trelina Energy Storage — verified asset snapshot

FieldValue
Queue IDNYISO-C24-207
LocationSeneca, New York
TechnologyBattery
DeveloperNextEra Energy Resources Interconnection Holdings, LLC
Market / regionNYISO
Point of interconnectionBorder City to Station 168 115 kV
Queue date2024-09-19
Proposed COD2030-12-01