Query
Timber Cove Solar SLF
Type
Entity Briefing
Entity
Timber Cove Solar SLF
Generated
2026-10-19T22:34:05.240Z

Briefing on Timber Cove Solar SLF

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
101 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2027-04-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Timber Cove Solar SLF is a 101 MW Solar+Battery project in Texas, currently active.

Freestone Solar, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-04-01.

Queue ID
ERCOT-24INR0532
Location
Freestone, Texas
Technology
Solar+Battery
Developer
Freestone Solar, LLC
Market / region
ERCOT
Point of interconnection
Tap 138 kV 212 Winkler - 3510 Pin Oak

What stands out

1

Timber Cove Solar SLF is a 101 MW Solar+Battery project in Texas with status active.

2

Freestone Solar, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-04-01.

Market and operating context

Queue date
2023-05-22
Proposed COD
2027-04-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Timber Cove Solar SLF — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0532
LocationFreestone, Texas
TechnologySolar+Battery
DeveloperFreestone Solar, LLC
Market / regionERCOT
Point of interconnectionTap 138 kV 212 Winkler - 3510 Pin Oak
Queue date2023-05-22
Proposed COD2027-04-01