Briefing on Symphony BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
612 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-07-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Symphony BESS is a 612 MW Battery project in Texas, currently active.

Symphony BESS, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-07-01.

Queue ID
ERCOT-26INR0466
Location
Austin, Texas
Technology
Battery
Developer
Symphony BESS, LLC
Market / region
ERCOT
Point of interconnection
46220 PETERS

What stands out

1

Symphony BESS is a 612 MW Battery project in Texas with status active.

2

Symphony BESS, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-07-01.

Market and operating context

Queue date
2025-02-14
Proposed COD
2028-07-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Symphony BESS — verified asset snapshot

FieldValue
Queue IDERCOT-26INR0466
LocationAustin, Texas
TechnologyBattery
DeveloperSymphony BESS, LLC
Market / regionERCOT
Point of interconnection46220 PETERS
Queue date2025-02-14
Proposed COD2028-07-01