Briefing on Sweetwater 4 Repower

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
421 MW
Proposed capacity
active
Current status
Wind
Technology
ERCOT
Market / region
2029-02-01
Proposed COD
Briefing/projectactive

Sweetwater 4 Repower is a 421 MW Wind project in Texas, currently active.

Sweetwater Wind 4 LLC is the reported developer. Proposed COD is 2029-02-01.

Queue ID
ERCOT-29INR0325
Location
Nolan, Texas
Technology
Wind
Developer
Sweetwater Wind 4 LLC
Market / region
ERCOT
Point of interconnection
<71050> <L_BITTCR5_1Y> <345kV>

What stands out

1

Sweetwater 4 Repower is a 421 MW Wind project in Texas with status active.

2

Sweetwater Wind 4 LLC is the reported developer.

3

proposed COD is 2029-02-01.

Market and operating context

Queue date
2026-04-22
Proposed COD
2029-02-01

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Sweetwater 4 Repower — verified asset snapshot

FieldValue
Queue IDERCOT-29INR0325
LocationNolan, Texas
TechnologyWind
DeveloperSweetwater Wind 4 LLC
Market / regionERCOT
Point of interconnection<71050> <L_BITTCR5_1Y> <345kV>
Queue date2026-04-22
Proposed COD2029-02-01