Star Grass Renewable Energy Solar SLF is a 150 MW Solar+Battery project in Texas, currently active.
Star Grass Renewable Energy LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-09-14.
- Queue ID
- ERCOT-28INR0195
- Location
- Eastland, Texas
- Technology
- Solar+Battery
- Developer
- Star Grass Renewable Energy LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 138kV 6310 Putnam - 3378 Carbon_8
What stands out
Star Grass Renewable Energy Solar SLF is a 150 MW Solar+Battery project in Texas with status active.
Star Grass Renewable Energy LLC is the reported developer.
The reported queue phase is Facility Study; proposed COD is 2029-09-14.
Latest linked story: “Scout Clean Energy celebrates its first completed solar project” (Solar Power World, 2024-11-22).
Market and operating context
- Queue date
- 2025-02-14
- Proposed COD
- 2029-09-14
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.