2.1 GW
Proposed capacity
active
Current status
Solar+Battery
Technology
CAISO
Market / region
2030-04-30
Proposed COD
Cluster 15
Queue phase
Briefing/projectactive

Stanley is a 2.1 GW Solar+Battery project in Arizona, currently active.

The reported queue phase is Cluster 15. Proposed COD is 2030-04-30.

Queue ID
CAISO-2331
Location
Maricopa, Arizona
Technology
Solar+Battery
Market / region
CAISO
Point of interconnection
CIELO AZUL 500 kV

What stands out

1

Stanley is a 2.1 GW Solar+Battery project in Arizona with status active.

2

The reported queue phase is Cluster 15; proposed COD is 2030-04-30.

Market and operating context

Queue date
2023-04-17
Proposed COD
2030-04-30
IA status
Not Started
Study phase
Cluster 15
Service type
ERIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Stanley — verified asset snapshot

FieldValue
Queue IDCAISO-2331
LocationMaricopa, Arizona
TechnologySolar+Battery
Market / regionCAISO
Point of interconnectionCIELO AZUL 500 kV
Queue date2023-04-17
Proposed COD2030-04-30
IA statusNot Started