Solace Storage is a 322 MW Solar+Battery project in Texas, currently active.
IP Quantum BESS, is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-06-01.
- Queue ID
- ERCOT-26INR0309
- Location
- Haskell, Texas
- Technology
- Solar+Battery
- Developer
- IP Quantum BESS,
- Market / region
- ERCOT
- Point of interconnection
- tap 345kV 1430 Graham - 1048 Tonkawas
What stands out
Solace Storage is a 322 MW Solar+Battery project in Texas with status active.
IP Quantum BESS, is the reported developer.
The reported queue phase is IA Executed; proposed COD is 2026-06-01.
Latest linked story: “Vistra Energy adds Baldwin, Joppa coal-fired power plants to closures list” (The Labor Tribune, 2020-10-12).
Market and operating context
- Queue date
- 2024-03-22
- Proposed COD
- 2026-06-01
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.