Solace Storage (ERCOT-26INR0309) — Project Summary

Queue ID
ERCOT-26INR0309
Capacity
321.79 MW
Technology
Solar+Battery
Status
active
Location
Haskell, TX
Region
ERCOT
Developer
IP Quantum BESS, LLC
IA Status
IA Executed

Solace Storage

ERCOT-26INR0309BetaActiveBatteryBatteryERCOTLBNL + Live

321.79 MW generation in Haskell, TX · In queue since March 2024 · Proposed COD September 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

321.79 MW

Capacity

1

Components

Battery

2y 8m

In Queue

IA Executed

IA Phase

Signed Mar 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1 year

IA → COD

1y 6m

Total Duration

1 year

Schedule

3 months past proposed COD

Construction75%
Queue EntryMar 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMar 21, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-09-01

Queue history
26INR0309 · 32 monthly ERCOT reports, Feb 2024 – Sep 2026

Projected COD moved

4 times

Sep 2026 → Sep 2026

Net change

0 months

first report to latest

Capacity

321 → 322 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 22, 2024
Facilities study approvedJun 9, 2025
Interconnection agreement signedMar 21, 2025
Approved for energizationJan 30, 2026
Approved for synchronizationMar 3, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 6y 1m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest activitycorporate_restructuringThe Labor Tribune · 2020-10-12

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Sep 1, 2026
From queue filing
Developer in saved assessment
IP Quantum BESS, LLC
Sources agreed at research time
Status at research time
IA Executed
Active in the ERCOT queue with the IA executed on 2025-03-21 and PGC registration filed in Nov 2025. ercotqueue.com lists the project as 'Commissioned', which suggests it is at or near commissioning, but no explicit construction or energization announcement was found.
Financing
Not recorded

Milestones in this assessment

IA executedMar 21, 2025Latest in this assessment

Oncor and IP Quantum BESS, LLC executed the Standard Generation Interconnection Agreement for Solace Storage (26INR0309).

interchange.puc.texas.gov
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. interchange.puc.texas.gov/Documents/35077_2113_1490346.PDF
  2. interchange.puc.texas.gov/Documents/58900_4_1560958.PDF
  3. ercotqueue.com/project/26INR0309
  4. ercotqueue.com/developer/ip-quantum-bess-llc
  5. cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0309/solace-storage

Commercial operation date: LBNL proposed COD is 2026-09-01, and Cleanview's 'Expected online 2026' is consistent with it. Texas PUC records show IP Quantum BESS registering as a power generation company in Oct–Nov 2025 for the 320 MW unit, which fits a 2026 online date. No source gives a different date.

Developer: The Texas PUC interconnection agreement and PGC registration, and ercotqueue.com, all name IP Quantum BESS, LLC, matching LBNL. No source names a parent company. The Vistra Energy news fact is a 2020 article about coal plant closures and is unrelated to this project, so I discarded it.

Status: LBNL shows IA Executed and active. The Oncor IA filing and the PUC PGC registration for a 320 MW storage unit confirm the project is progressing toward operation. No source confirms it is online or under construction.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Solace Storage project is a proposed 321.02 MW battery energy storage system located in Haskell County, Texas. The project, developed by IP Quantum BESS, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0309, with a queue entry date of March 22, 2024. The proposed commercial operation date is June 1, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.

The proposed project will interconnect at the tap 345kV 1430 Graham - 1048 Tonkawas. Solace Storage has been the subject of recent news coverage, including reports related to industry developments and business deals.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Haskell

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

IP Quantum BESS, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap 345kV 1430 Graham - 1048 Tonkawas

Data Source

LBNL + Live

CompanyVistra EnergyThe Labor Tribune · 2020-10-12
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
GRSES_UNIT1
POI Substation
Graham Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.