Briefing on Skeeter Solar

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
251 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2028-12-02
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Skeeter Solar is a 251 MW Solar project in Texas, currently active.

Mesquite Solar, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-12-02.

Queue ID
ERCOT-29INR0026
Location
Jones, Texas
Technology
Solar
Developer
Mesquite Solar, LLC
Market / region
ERCOT
Point of interconnection
345 kV SWEETWATER EAST (11420) - LONG CREEK (1435)

What stands out

1

Skeeter Solar is a 251 MW Solar project in Texas with status active.

2

Mesquite Solar, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-12-02.

Market and operating context

Queue date
2024-06-03
Proposed COD
2028-12-02
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Skeeter Solar — verified asset snapshot

FieldValue
Queue IDERCOT-29INR0026
LocationJones, Texas
TechnologySolar
DeveloperMesquite Solar, LLC
Market / regionERCOT
Point of interconnection345 kV SWEETWATER EAST (11420) - LONG CREEK (1435)
Queue date2024-06-03
Proposed COD2028-12-02