Briefing/projectactive
SILVER STAR SOLAR is a 1 GW Solar+Battery project in Nevada, currently active.
The reported queue phase is C14. Proposed COD is 2028-12-01.
- Queue ID
- CAISO-2142
- Location
- Nye, Nevada
- Technology
- Solar+Battery
- Market / region
- CAISO
- Point of interconnection
- Lathrop Wells Substation 230 kV
What stands out
1
SILVER STAR SOLAR is a 1 GW Solar+Battery project in Nevada with status active.
2
The reported queue phase is C14; proposed COD is 2028-12-01.
3
Latest linked story: “NV Energy, NextEra and Leeward among winning bids for gigawatts of solar in Nevada desert” (Solar Power World, 2023-06-28).
Market and operating context
- Queue date
- 2021-04-15
- Proposed COD
- 2028-12-01
- IA status
- IA Executed
- Study phase
- C14
- Service type
- ERIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.