SILVER STAR SOLAR (CAISO-2142) — Project Summary

Queue ID
CAISO-2142
Capacity
1033.5276 MW
Technology
Solar+Battery
Status
active
Location
Nye, NV
Region
CAISO
Developer
—
IA Status
IA Executed

SILVER STAR SOLAR

CAISO-2142BetaActiveSolarBatteryCAISOLBNL + Live

1,033.528 MW hybrid in Nye, NV · In queue since April 2021 · Proposed COD December 2028

BA: NEVPISO/RTO: CAISONERC: WECCRC: SPPW

1,033.528 MW

Capacity

2

Components

Solar + Battery

5y 7m

In Queue

IA Executed

IA Phase

Signed Apr 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

4 years

IA → COD

3y 8m

Total Duration

4 years

Study Phase

C14

Construction75%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementApr 8, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Active sheet; IA Executed; C14

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2028-12-01

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Dec 1, 2028
From queue filing
Developer in saved assessment
Leeward Renewable Energy
Filed as Silver Star Solar 1, LLC
Status at research time
IA Executed
Active in queue with IA executed (2025-04-08); federal permitting (BLM NEPA and right-of-way, FAST-41) is still pending with its timetable extended in Nov 2025. No construction has started.
Financing
Not recorded

Milestones in this assessment

IA executedApr 8, 2025Latest in this assessment

LBNL records the IA as executed on 2025-04-08, and the CAISO LGIA list shows an LGIA for Silver Star Solar I, LLC. The date comes from LBNL, not from the CAISO document.

caiso.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. lreus.com/projects/silver-star-solar/
  2. lreus.com/wp-content/uploads/2025/11/SilverStarSolar-FactSheet.pdf
  3. cleanview.co/power-projects/planned/solar-farms/nevada/2142_photovoltaic/silver-star-solar
  4. caiso.com/documents/list-of-large-generator-interconnection-agreements-and-small-generator-interconnection-agreements.pdf
  5. permits.performance.gov/sites/permits.dot.gov/files/2025-11/Silver%20Star%20Solar%20Executive%20Director%20Determination_11-13-2025.pdf

Commercial operation date: LBNL proposed COD is 2028-12-01, and Cleanview lists the project as 'Expected online 2028'. No developer press release gives a different date. Cleanview may simply mirror the queue data, and the BLM extended the federal permitting timetable in Nov 2025, so slippage is possible.

Developer: The LBNL developer field is null. Leeward Renewable Energy's project page and fact sheet say 'LRE subsidiary Silver Star Solar 1, LLC is proposing' the project, and the CAISO LGIA list names 'Silver Star Solar I, LLC' as interconnection customer. The 2023 news extraction lists NV Energy, NextEra and Leeward only as generic auction winners, so I did not use it to attribute the project.

Status: LBNL shows the status as active and the IA as executed, and the CAISO LGIA list names Silver Star Solar I, LLC. The FAST-41 dashboard and the Nov 2025 Executive Director determination show BLM permitting is incomplete, so the project is not yet in construction.

Project lifecycle
as of 2023-06-28
OperationalNoSolar Power World · 2023-06-28
TechnologySolarSolar Power World · 2023-06-28
DeveloperNV Energy, NextEra Energy Resources, Leeward Renewable EnergySolar Power World · 2023-06-28
Permit decisionpendingSolar Power World · 2023-06-28

About

Saved background

Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Silver Star Solar project is a proposed 1033.53 MW hybrid solar and battery energy storage project located in Nye County, Nevada. The development project consists of 516.76 MW of solar photovoltaic generation paired with 516.76 MW of battery energy storage. The project is listed in the CAISO interconnection queue as entry CAISO-2142, with a queue entry date of April 15, 2021, and a proposed commercial operation date of December 1, 2028. The interconnection agreement status is listed as "In Progress (unknown study)".

The proposed project is interconnected to the grid at the Lathrop Wells Substation 230 kV. The project has appeared in recent news coverage related to industry and regulatory matters.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • CAISO queue source as of: Oct 24, 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

NV

County

Nye

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

—

Utility

GLW

Entity

CAISO

Service Type

ERIS

Point of Interconnection

Lathrop Wells Substation 230 kV

Data Source

LBNL + Live

Deal value$105.2MSolar Power World · 2023-06-28
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Technology
Solar516.764 MW · 50%
Battery516.764 MW · 50%
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_NP15_GEN-APND
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.