Briefing on Seine BESS

Entity Briefing
Generated Oct 6, 2026·Dataset freshness not reported
301 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-10-01
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Seine BESS is a 301 MW Battery project in Texas, currently active.

BRP Seine BESS LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-10-01.

Queue ID
ERCOT-23INR0140
Location
Foard, Texas
Technology
Battery
Developer
BRP Seine BESS LLC
Market / region
ERCOT
Point of interconnection
60500 Edith Clarke 345kV

What stands out

1

Seine BESS is a 301 MW Battery project in Texas with status active.

2

BRP Seine BESS LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2027-10-01.

Market and operating context

Queue date
2020-12-03
Proposed COD
2027-10-01
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Seine BESS — verified asset snapshot

FieldValue
Queue IDERCOT-23INR0140
LocationFoard, Texas
TechnologyBattery
DeveloperBRP Seine BESS LLC
Market / regionERCOT
Point of interconnection60500 Edith Clarke 345kV
Queue date2020-12-03
Proposed COD2027-10-01