Seine BESS (ERCOT-23INR0140) — Project Summary

Queue ID
ERCOT-23INR0140
Capacity
301.19 MW
Technology
Battery
Status
active
Location
Foard, TX
Region
ERCOT
Developer
BRP Seine BESS LLC
IA Status
IA Executed

Seine BESS

ERCOT-23INR0140BetaActiveBatteryERCOTLBNL + Live

301.19 MW storage in Foard, TX · In queue since December 2020 · Proposed COD October 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

301.19 MW

Capacity

1

Components

Battery

5y 11m

In Queue

IA Executed

IA Phase

Signed Dec 2024

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

4 years

IA → COD

2y 10m

Total Duration

4 years

Construction75%
Queue EntryDec 3, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 1, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-10-01

Queue history
23INR0140 · 71 monthly ERCOT reports, Nov 2020 – Sep 2026

Projected COD moved

3 times

Oct 2023 → Oct 2027

Net change

+48 months

first report to latest

Capacity

302 → 309 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedDec 3, 2020
Facilities study approvedSep 1, 2026
Interconnection agreement signedDec 1, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Oct 1, 2027
From queue filing
Developer in saved assessment
BRP Seine BESS LLC
From queue filing
Status at research time
IA Executed
Active in the ERCOT queue. The standard generation interconnection agreement with Electric Transmission Texas was filed 12/3/2024, and IA and FIS are complete. No construction start or financing close has been announced.
Financing
Not recorded

Milestones in this assessment

IA executedDec 2024Latest in this assessment

ERCOT standard generation interconnection agreement between Electric Transmission Texas, LLC and BRP Seine BESS LLC filed 12/3/2024.

interchange.puc.texas.gov
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. interchange.puc.texas.gov/Search/Filings?ControlNumber=35077&ItemMatch=0&SortBy=ItemNumber&SortOrder=Descending
  2. cleanview.co/power-projects/planned/battery-storage-projects/texas/23INR0140/seine-bess
  3. ercotqueue.com/project/23INR0140
  4. interconnection.fyi/project/ercot-23inr0140

Commercial operation date: Cleanview shows 'expected to come online in October 2027', matching the LBNL proposed COD of 2027-10-01. It appears to mirror the ERCOT queue data rather than give an independent developer target. No press release or news article gives a different date.

Developer: The LBNL filing, the PUC Interchange interconnection agreement and the ERCOT queue trackers all name BRP Seine BESS LLC. No source names a parent or operating company, so the shell-versus-parent question can't be resolved from this evidence.

Status: The PUC Interchange filing for the BRP Seine BESS interconnection agreement confirms the LBNL IA Executed status (IA date 2024-12). ercotqueue.com also lists IA and FIS as complete. No source shows withdrawal or construction.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Seine BESS project is a proposed 301.19 MW battery storage project located in Foard County, Texas. Developed by BRP Seine BESS LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0140, with a queue entry date of December 3, 2020.

The proposed commercial operation date for the Seine BESS project is December 1, 2027. Its interconnection status is currently in the Facility Study phase, and its point of interconnection is the 60500 Edith Clarke 345kV. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Foard

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BRP Seine BESS LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

60500 Edith Clarke 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
FOARDCTY_ALL
POI Substation
Edith Clarke Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.