Briefing on Sbranch Solar

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
234 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2026-04-30
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Sbranch Solar is a 234 MW Solar project in Texas, currently active.

ConnectGen is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-04-30.

Queue ID
ERCOT-22INR0205
Location
Wharton, Texas
Technology
Solar
Developer
ConnectGen
Market / region
ERCOT
Point of interconnection
Tap 138kV 44190 East Bernard - 44130 Caney

What stands out

1

Sbranch Solar is a 234 MW Solar project in Texas with status active.

2

ConnectGen is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-04-30.

Market and operating context

Queue date
2019-01-03
Proposed COD
2026-04-30
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Sbranch Solar — verified asset snapshot

FieldValue
Queue IDERCOT-22INR0205
LocationWharton, Texas
TechnologySolar
DeveloperConnectGen
Market / regionERCOT
Point of interconnectionTap 138kV 44190 East Bernard - 44130 Caney
Queue date2019-01-03
Proposed COD2026-04-30