Briefing/projectactive
Sbranch Solar is a 234 MW Solar project in Texas, currently active.
ConnectGen is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-04-30.
- Queue ID
- ERCOT-22INR0205
- Location
- Wharton, Texas
- Technology
- Solar
- Developer
- ConnectGen
- Market / region
- ERCOT
- Point of interconnection
- Tap 138kV 44190 East Bernard - 44130 Caney
What stands out
1
Sbranch Solar is a 234 MW Solar project in Texas with status active.
2
ConnectGen is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2026-04-30.
Market and operating context
- Queue date
- 2019-01-03
- Proposed COD
- 2026-04-30
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.