Briefing on San Perlita BESS 2

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
150 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2025-12-15
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

San Perlita BESS 2 is a 150 MW Battery project in Texas, currently active.

RWE Renewables is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2025-12-15.

Queue ID
ERCOT-23INR0497
Location
Willacy, Texas
Technology
Battery
Developer
RWE Renewables
Market / region
ERCOT
Point of interconnection
8601 Cebolla 345kV

What stands out

1

San Perlita BESS 2 is a 150 MW Battery project in Texas with status active.

2

RWE Renewables is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2025-12-15.

Market and operating context

Queue date
2022-06-02
Proposed COD
2025-12-15
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

San Perlita BESS 2 — verified asset snapshot

FieldValue
Queue IDERCOT-23INR0497
LocationWillacy, Texas
TechnologyBattery
DeveloperRWE Renewables
Market / regionERCOT
Point of interconnection8601 Cebolla 345kV
Queue date2022-06-02
Proposed COD2025-12-15