Briefing on Roadrunner Crossing Wind (Uprate)

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
3 MW
Proposed capacity
active
Current status
Wind+Battery
Technology
ERCOT
Market / region
2027-06-30
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Roadrunner Crossing Wind (Uprate) is a 3 MW Wind+Battery project in Texas, currently active.

Roadrunner Wind, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-06-30.

Queue ID
ERCOT-26INR0726
Location
Eastland, Texas
Technology
Wind+Battery
Developer
Roadrunner Wind, LLC
Market / region
ERCOT
Point of interconnection
68051 Reata 345kV

What stands out

1

Roadrunner Crossing Wind (Uprate) is a 3 MW Wind+Battery project in Texas with status active.

2

Roadrunner Wind, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-06-30.

Market and operating context

Queue date
2025-12-23
Proposed COD
2027-06-30
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Roadrunner Crossing Wind (Uprate) — verified asset snapshot

FieldValue
Queue IDERCOT-26INR0726
LocationEastland, Texas
TechnologyWind+Battery
DeveloperRoadrunner Wind, LLC
Market / regionERCOT
Point of interconnection68051 Reata 345kV
Queue date2025-12-23
Proposed COD2027-06-30