Briefing on RIVERBEND SOLAR SLF

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
302 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2027-12-31
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

RIVERBEND SOLAR SLF is a 302 MW Solar+Battery project in Texas, currently active.

Riverbend Renewables, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-12-31.

Queue ID
ERCOT-25INR0297
Location
Falls, Texas
Technology
Solar+Battery
Developer
Riverbend Renewables, LLC
Market / region
ERCOT
Point of interconnection
TAP 345 KV LINE FROM TRADINGHOUSE (#3405) TO TEMPLE PECAN CREEK (#3412) SUBSTATIONS

What stands out

1

RIVERBEND SOLAR SLF is a 302 MW Solar+Battery project in Texas with status active.

2

Riverbend Renewables, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-12-31.

Market and operating context

Queue date
2023-03-08
Proposed COD
2027-12-31
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

RIVERBEND SOLAR SLF — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0297
LocationFalls, Texas
TechnologySolar+Battery
DeveloperRiverbend Renewables, LLC
Market / regionERCOT
Point of interconnectionTAP 345 KV LINE FROM TRADINGHOUSE (#3405) TO TEMPLE PECAN CREEK (#3412) SUBSTATIONS
Queue date2023-03-08
Proposed COD2027-12-31