Briefing on Riverbank Energy

Entity Briefing
Generated Oct 13, 2026·Dataset freshness not reported
200 MW
Proposed capacity
active
Current status
Battery
Technology
PJM
Market / region
2024-05-31
Proposed COD
TC1
Queue phase
Briefing/projectactive

Riverbank Energy is a 200 MW Battery project in Illinois, currently active.

Lincoln Reserve Energy, LLC is the reported developer. The reported queue phase is TC1. Proposed COD is 2024-05-31.

Queue ID
PJM-AF2-441
Location
Cook, Illinois
Technology
Battery
Developer
Lincoln Reserve Energy, LLC
Market / region
PJM
Point of interconnection
Burnham 138kV

What stands out

1

Riverbank Energy is a 200 MW Battery project in Illinois with status active.

2

Lincoln Reserve Energy, LLC is the reported developer.

3

The reported queue phase is TC1; proposed COD is 2024-05-31.

Market and operating context

Queue date
2020-03-31
Proposed COD
2024-05-31
IA status
Feasibility Study
Study phase
TC1
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Riverbank Energy — verified asset snapshot

FieldValue
Queue IDPJM-AF2-441
LocationCook, Illinois
TechnologyBattery
DeveloperLincoln Reserve Energy, LLC
Market / regionPJM
Point of interconnectionBurnham 138kV
Queue date2020-03-31