Red Egret BESS
Type
Entity Briefing
Entity
Red Egret BESS
State
TN
Technology
battery
Generated
2026-10-19T01:13:39.059Z

Briefing on Red Egret BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
311 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2026-08-31
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Red Egret BESS is a 311 MW Battery project in Texas, currently active.

Red Egret LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-08-31.

Queue ID
ERCOT-24INR0281
Location
Galveston, Texas
Technology
Battery
Developer
Red Egret LLC
Market / region
ERCOT
Point of interconnection
38820 FREEWAY PARK 138KV

What stands out

1

Red Egret BESS is a 311 MW Battery project in Texas with status active.

2

Red Egret LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-08-31.

Market and operating context

Queue date
2022-03-14
Proposed COD
2026-08-31
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Red Egret BESS — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0281
LocationGalveston, Texas
TechnologyBattery
DeveloperRed Egret LLC
Market / regionERCOT
Point of interconnection38820 FREEWAY PARK 138KV
Queue date2022-03-14
Proposed COD2026-08-31