Red Egret BESS
310.58 MW storage in Galveston, TX · In queue since March 2022 · Proposed COD November 2027
310.58 MW
Capacity
1
Components
Battery
4y 8m
In Queue
IA Executed
IA Phase
Signed Jun 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 3m
IA → COD
4y 5m
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2027-11-17
Projected COD moved
7 times
Dec 2024 → Nov 2027
Net change
+35 months
first report to latest
Capacity
300 → 311 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection agreement executed for Red Egret BESS (ERCOT 24INR0281), per queue data.
interconnection.fyiTexas City approved Spearmint's 300MW/600MWh BESS, with the date inferred from the article's age of about 14 months.
energy-storage.newsSpearmint closed about $450M in project financing for the 600-MWh Red Egret BESS.
renewablesnow.comProject expected to commence operations in 2027.
finance.yahoo.comResearch sources and reasoning (7 recorded sources)
high confidence at research time
- power-technology.com/news/spearmint-energy-450m-red-egret-bess/
- constructionreviewonline.com/red-egret-bess-project-in-texas-closes-financing-as-spearmint-bids-to-support-ercot-power-market/
- energy-storage.news/spearmint-energy-gets-greenlight-for-texas-city-bess-as-a-further-860mw-of-capacity-withdrawn-from-ercot-queue/
- galvnews.com/news/texas-city-oks-next-steps-for-300-megawatt-battery-energy-storage-facility/article_e1bb7f03-933e-55e2-a5d9-91998cff3a0d.html
- renewablesnow.com/news/spearmint-inks-financing-for-600-mwh-red-egret-bess-project-in-texas-1295126/
- finance.yahoo.com/sectors/energy/articles/spearmint-energy-secures-450m-red-090904458.html
- interconnection.fyi/project/ercot-24inr0281
Commercial operation date: The May 2026 financing coverage says "The Red Egret project is expected to commence operations in 2027," which matches the LBNL proposed COD of 2027-11-17 at the year level. No source gives a more specific date.
Developer: LBNL lists the project-specific shell "Red Egret LLC". Trade press (Power Technology, Construction Review, Renewables Now) consistently names Spearmint Energy as the developer that secured financing and is building the project.
Status: LBNL shows IA Executed and an active queue status, and the financing closing in May 2026 shows the project is advancing. No source confirms groundbreaking or operation, so Construction or Online would overstate it.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Red Egret BESS project is a proposed 310.58 MW battery storage project located in Galveston County, Texas. The developer is Red Egret LLC. It is interconnected within the ERCOT region under queue ID ERCOT-24INR0281.
The project entered the interconnection queue on March 14, 2022, with a proposed commercial operation date of August 31, 2026. The Interconnection Agreement (IA) for the project has been executed as of June 7, 2023. The Point of Interconnection (POI) is the 38820 FREEWAY PARK 138KV.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Galveston
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Red Egret LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
38820 FREEWAY PARK 138KV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- TOPAZ_ALL
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.