Ramsey Storage is a 201 MW Battery project in Texas, currently active.
Hecate Energy Ramsey Storage LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2028-06-30.
- Queue ID
- ERCOT-21INR0505
- Location
- Wharton, Texas
- Technology
- Battery
- Developer
- Hecate Energy Ramsey Storage LLC
- Market / region
- ERCOT
- Point of interconnection
- 44200 Hillje 345kV
What stands out
1
Ramsey Storage is a 201 MW Battery project in Texas with status active.
2
Hecate Energy Ramsey Storage LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2028-06-30.
Market and operating context
- Queue date
- 2020-05-20
- Proposed COD
- 2028-06-30
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.