Query
Purple Sage BESS 2
Type
Entity Briefing
Entity
Purple Sage BESS 2
State
TN
Technology
battery
Generated
2026-10-19T13:14:35.342Z

Briefing on Purple Sage BESS 2

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
156 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-05-30
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Purple Sage BESS 2 is a 156 MW Battery project in Texas, currently active.

Purple Sage, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-05-30.

Queue ID
ERCOT-25INR0392
Location
Collin, Texas
Technology
Battery
Developer
Purple Sage, LLC
Market / region
ERCOT
Point of interconnection
Anna 345 kV Bus# 2373

What stands out

1

Purple Sage BESS 2 is a 156 MW Battery project in Texas with status active.

2

Purple Sage, LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2027-05-30.

Market and operating context

Queue date
2023-03-08
Proposed COD
2027-05-30
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Purple Sage BESS 2 — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0392
LocationCollin, Texas
TechnologyBattery
DeveloperPurple Sage, LLC
Market / regionERCOT
Point of interconnectionAnna 345 kV Bus# 2373
Queue date2023-03-08
Proposed COD2027-05-30