Pioneer Hutt Solar (Alternative POI) is a 116 MW Solar project in Texas, currently active.
NextEra Energy Interconnection Holdings LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-07-01.
- Queue ID
- ERCOT-26INR0121
- Location
- Midland, Texas
- Technology
- Solar
- Developer
- NextEra Energy Interconnection Holdings LLC
- Market / region
- ERCOT
- Point of interconnection
- TAP 345kV 11028 Odessa Ehv - 59901 Grelton (West C)
What stands out
1
Pioneer Hutt Solar (Alternative POI) is a 116 MW Solar project in Texas with status active.
2
NextEra Energy Interconnection Holdings LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2028-07-01.
Market and operating context
- Queue date
- 2023-06-28
- Proposed COD
- 2028-07-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.