Briefing on Permian I Wind

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
637 MW
Proposed capacity
active
Current status
Wind
Technology
ERCOT
Market / region
2030-06-30
Proposed COD
Briefing/projectactive

Permian I Wind is a 637 MW Wind project in Texas, currently active.

S&S Renewables, LLC is the reported developer. Proposed COD is 2030-06-30.

Queue ID
ERCOT-30INR0086
Location
Pecos, Texas
Technology
Wind
Developer
S&S Renewables, LLC
Market / region
ERCOT
Point of interconnection
Tap TNMP White Baker (38435)–Bottlebrush(38441) 345-kV double-circuit

What stands out

1

Permian I Wind is a 637 MW Wind project in Texas with status active.

2

S&S Renewables, LLC is the reported developer.

3

proposed COD is 2030-06-30.

4

Latest linked story: “Gina McCarthy: ‘U.S. companies may not be putting their hands up, but they are still investing in clean energy’” (Reuters, 2025-05-12).

Market and operating context

Queue date
2026-01-26
Proposed COD
2030-06-30

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Permian I Wind — verified asset snapshot

FieldValue
Queue IDERCOT-30INR0086
LocationPecos, Texas
TechnologyWind
DeveloperS&S Renewables, LLC
Market / regionERCOT
Point of interconnectionTap TNMP White Baker (38435)–Bottlebrush(38441) 345-kV double-circuit
Queue date2026-01-26