Briefing on Peregrine BESS 2

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
150 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2027-07-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Peregrine BESS 2 is a 150 MW Solar+Battery project in Texas, currently active.

CED Development Inc. is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-07-01.

Queue ID
ERCOT-25INR0078
Location
Goliad, Texas
Technology
Solar+Battery
Developer
CED Development Inc.
Market / region
ERCOT
Point of interconnection
8673 RAPTOR7A 345kV

What stands out

1

Peregrine BESS 2 is a 150 MW Solar+Battery project in Texas with status active.

2

CED Development Inc. is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-07-01.

4

Latest linked story: “Battery storage facility coming to League City” (Community Impact | News, 2024-09-27).

Market and operating context

Queue date
2022-08-05
Proposed COD
2027-07-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Peregrine BESS 2 — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0078
LocationGoliad, Texas
TechnologySolar+Battery
DeveloperCED Development Inc.
Market / regionERCOT
Point of interconnection8673 RAPTOR7A 345kV
Queue date2022-08-05
Proposed COD2027-07-01