Owens Solar is a 204 MW Solar project in Texas, currently suspended.
Owens Solar LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2025-12-31.
- Queue ID
- ERCOT-24INR0213
- Location
- Bosque, Texas
- Technology
- Solar
- Developer
- Owens Solar LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 138kV line between 177 BOSQUE and 181 Cayote
What stands out
Owens Solar is a 204 MW Solar project in Texas with status suspended.
Owens Solar LLC is the reported developer.
The reported queue phase is Facility Study; proposed COD is 2025-12-31.
Latest linked story: “‘The horse is out of the barn’: DeKalb County Board approves 3 industrial solar projects by Leeward Energy, Samsung” (Shaw Local, 2021-11-18).
Market and operating context
- Queue date
- 2022-02-06
- Proposed COD
- 2025-12-31
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.