Orbit Energy Storage is a 502 MW Battery project in Texas, currently active.
GCI Orbit Energy Storage, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-06-01.
- Queue ID
- ERCOT-27INR0082
- Location
- Bexar, Texas
- Technology
- Battery
- Developer
- GCI Orbit Energy Storage, LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345 kV Calaveras Power Station (BUS #5400) to VON_ROSE (BUS #5475)
What stands out
Orbit Energy Storage is a 502 MW Battery project in Texas with status active.
GCI Orbit Energy Storage, LLC is the reported developer.
The reported queue phase is Facility Study; proposed COD is 2027-06-01.
Latest linked story: “Powering new investments in the clean energy space” (J.P. Morgan, 2024-07-11).
Market and operating context
- Queue date
- 2023-11-30
- Proposed COD
- 2027-06-01
- IA status
- Facility Study
- Study phase
- Facility Study