Orbit Energy Storage
501.94 MW storage in Bexar, TX · In queue since November 2023 · Proposed COD June 2027
501.94 MW
Capacity
1
Components
Battery
3 years
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
Projected COD moved
0 times
Jun 2027 → Jun 2027
Net change
0 months
first report to latest
Capacity
502 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (2 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-27inr0082
- groundtrace.io/developers/gci-orbit-energy-storage-llc-eyc6bhygioxmu
Commercial operation date: Only the LBNL/ERCOT filing gives a date (proposed COD 2027-06-01, Facility Study stage). No press release or news item in the search results gives a different target.
Developer: Only the filing entity (GCI Orbit Energy Storage, LLC) is confirmed, by interconnection.fyi and Groundtrace, and no parent company could be identified. The news-extracted 'Ørsted' attribution comes from a generic J.P. Morgan–Ørsted tax equity page ($680M) that never names Orbit Energy Storage, Bexar County or ERCOT-27INR0082, so I did not adopt it.
Status: LBNL lists the project as active and interconnection.fyi confirms it is currently active in ERCOT. No source reports withdrawal, suspension or construction.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Orbit Energy Storage project is a proposed 501.94 MW battery storage project located in Bexar County, Texas. Developed by GCI Orbit Energy Storage, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0082, with a queue entry date of November 30, 2023. The proposed commercial operation date is June 1, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for the Orbit Energy Storage project is planned at the Tap 345 kV Calaveras Power Station to HOWARD_5. Recent news coverage indicates interest in the project, with articles focusing on grid implications and development progress.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bexar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
GCI Orbit Energy Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV Calaveras Power Station (BUS #5400) to VON_ROSE (BUS #5475)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.