Briefing/projectactive
Orange Grove BESS is a 61 MW Solar+Battery project in Texas, currently active.
Talitha Energy Project, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-04-30.
- Queue ID
- ERCOT-23INR0331
- Location
- Jim Wells, Texas
- Technology
- Solar+Battery
- Developer
- Talitha Energy Project, LLC
- Market / region
- ERCOT
- Point of interconnection
- 5660 Orange Grove Switching Station 138 kV
What stands out
1
Orange Grove BESS is a 61 MW Solar+Battery project in Texas with status active.
2
Talitha Energy Project, LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2027-04-30.
Market and operating context
- Queue date
- 2021-07-15
- Proposed COD
- 2027-04-30
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.