Briefing on Orange Grove BESS

Entity Briefing
Generated Oct 12, 2026·Dataset freshness not reported
61 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2027-04-30
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Orange Grove BESS is a 61 MW Solar+Battery project in Texas, currently active.

Talitha Energy Project, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-04-30.

Queue ID
ERCOT-23INR0331
Location
Jim Wells, Texas
Technology
Solar+Battery
Developer
Talitha Energy Project, LLC
Market / region
ERCOT
Point of interconnection
5660 Orange Grove Switching Station 138 kV

What stands out

1

Orange Grove BESS is a 61 MW Solar+Battery project in Texas with status active.

2

Talitha Energy Project, LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2027-04-30.

Market and operating context

Queue date
2021-07-15
Proposed COD
2027-04-30
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Orange Grove BESS — verified asset snapshot

FieldValue
Queue IDERCOT-23INR0331
LocationJim Wells, Texas
TechnologySolar+Battery
DeveloperTalitha Energy Project, LLC
Market / regionERCOT
Point of interconnection5660 Orange Grove Switching Station 138 kV
Queue date2021-07-15
Proposed COD2027-04-30