Briefing/projectactive
Wolf Bone North Energy Center is a 1.2 GW Gas project in Texas, currently active.
NRG Wolf Bone Energy Center LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-11-01.
- Queue ID
- ERCOT-29INR0162
- Location
- Reeves, Texas
- Technology
- Gas
- Developer
- NRG Wolf Bone Energy Center LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345 kV 60404 SOLTICE7A - 18669 TOYAHCRK_5 Ckt 1 Tap 345 kV 60404 SOLTICE7A - 18669 TOYAHCRK_5 Ckt 2
What stands out
1
Wolf Bone North Energy Center is a 1.2 GW Gas project in Texas with status active.
2
NRG Wolf Bone Energy Center LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2029-11-01.
Market and operating context
- Queue date
- 2025-10-21
- Proposed COD
- 2029-11-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.