MRR Solar is a 500 MW Solar project in Texas, currently active.
BOULEVARD ASSOCIATES, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2030-07-01.
- Queue ID
- ERCOT-30INR0053
- Location
- Pecos, Texas
- Technology
- Solar
- Developer
- BOULEVARD ASSOCIATES, LLC
- Market / region
- ERCOT
- Point of interconnection
- Solstice Substation #60384 -AEP
What stands out
MRR Solar is a 500 MW Solar project in Texas with status active.
BOULEVARD ASSOCIATES, LLC is the reported developer.
The reported queue phase is Facility Study; proposed COD is 2030-07-01.
Latest linked story: “Intersect Power’s 828MWp Lumina solar project in US begins operation” (Power Technology, 2024-01-12).
Market and operating context
- Queue date
- 2025-07-29
- Proposed COD
- 2030-07-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.