Briefing on MRG GOODY SOLAR

Entity Briefing
Generated Sep 18, 2026·Dataset freshness not reported
171 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2026-03-20
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

MRG GOODY SOLAR is a 171 MW Solar+Battery project in Texas, currently active.

MRG GOODY SOLAR PROJECT, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-03-20.

Queue ID
ERCOT-23INR0225
Location
Lamar, Texas
Technology
Solar+Battery
Developer
MRG GOODY SOLAR PROJECT, LLC
Market / region
ERCOT
Point of interconnection
Tap 138 kV Toco Switch (#1700) – Paris Switch (#1693)

What stands out

1

MRG GOODY SOLAR is a 171 MW Solar+Battery project in Texas with status active.

2

MRG GOODY SOLAR PROJECT, LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-03-20.

4

Latest linked story: “NextEra signs 2.5GW of renewable energy agreements with Meta for projects across US” (Energy-Storage.News, 2025-12-10).

Market and operating context

Queue date
2021-03-16
Proposed COD
2026-03-20
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

MRG GOODY SOLAR — verified asset snapshot

FieldValue
Queue IDERCOT-23INR0225
LocationLamar, Texas
TechnologySolar+Battery
DeveloperMRG GOODY SOLAR PROJECT, LLC
Market / regionERCOT
Point of interconnectionTap 138 kV Toco Switch (#1700) – Paris Switch (#1693)
Queue date2021-03-16
Proposed COD2026-03-20