Vast Sands Power I (TEF -Due Diligence) is a 440 MW Gas project in Texas, currently active.
Permian Power I LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2028-05-01.
- Queue ID
- ERCOT-28INR0105
- Location
- Ward, Texas
- Technology
- Gas
- Developer
- Permian Power I LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345kV 11010 Wolf Switch - 11188 Quarry Field Switch Ckt 2
What stands out
1
Vast Sands Power I (TEF -Due Diligence) is a 440 MW Gas project in Texas with status active.
2
Permian Power I LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2028-05-01.
Market and operating context
- Queue date
- 2024-07-22
- Proposed COD
- 2028-05-01
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.