Briefing on Monte Cristo II Wind

Entity Briefing
Generated Jul 29, 2026·Dataset freshness not reported
234 MW
Proposed capacity
active
Current status
Wind
Technology
ERCOT
Market / region
2028-12-31
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Monte Cristo II Wind is a 234 MW Wind project in Texas, currently active.

Monte Cristo Windpower II, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2028-12-31.

Queue ID
ERCOT-19INR0055
Location
Hidalgo, Texas
Technology
Wind
Developer
Monte Cristo Windpower II, LLC
Market / region
ERCOT
Point of interconnection
8574 Pomelo 345kV

What stands out

1

Monte Cristo II Wind is a 234 MW Wind project in Texas with status active.

2

Monte Cristo Windpower II, LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2028-12-31.

4

Latest linked story: “Rio Tinto signs 15-year renewable power deal with U.S. based TerraGen” (Reuters, 2025-11-14).

Market and operating context

Queue date
2017-04-11
Proposed COD
2028-12-31
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Monte Cristo II Wind — verified asset snapshot

FieldValue
Queue IDERCOT-19INR0055
LocationHidalgo, Texas
TechnologyWind
DeveloperMonte Cristo Windpower II, LLC
Market / regionERCOT
Point of interconnection8574 Pomelo 345kV
Queue date2017-04-11
Proposed COD2028-12-31