Monte Cristo II Wind
233.9 MW generation in Hidalgo, TX · In queue since April 2017 · Proposed COD December 2028
233.9 MW
Capacity
1
Components
Wind
9y 7m
In Queue
IA Executed
IA Phase
Signed Dec 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
8y 8m
IA → COD
3 years
Total Duration
8y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 18–36 months
Proposed COD: 2028-12-31
Projected COD moved
6 times
Dec 2019 → Dec 2028
Net change
+108 months
first report to latest
Capacity
200 → 234 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Hidalgo County Commissioners Court approved tax abatement agreement for wind farm
public.destinyhosted.comInterconnection Agreement executed with ERCOT
ercot.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- public.destinyhosted.com/hidaldocs/2025/CC/20250722_5216/100152_Monte_Cristo_Windpower_II_LLC_-_Tax_Abatement_agreement_7.22.2025.pdf
- ercot.com/files/docs/2026/03/05/Capacity-Changes-by-Fuel-Type-Charts_February_2026.xlsx
- businesswire.com/news/home/20251113632994/en/Terra-Gen-Expands-Clean-Energy-Portfolio-with-Commissioning-of-Monte-Cristo-I-Windpower-Project-in-Texas
- power-technology.com/news/terra-gen-commissions-windpower-project/
Commercial operation date: LBNL queue shows 2028-12-31 COD. No news coverage exists for Monte Cristo II specifically—all search results reference Monte Cristo I (238.5MW, commissioned Nov 2025). Tax abatement agreement from July 2025 confirms project existence but provides no COD update.
Developer: LBNL filing entity is 'Monte Cristo Windpower II, LLC' (project shell). Multiple Nov 2025 press releases confirm Terra-Gen owns and operates the adjacent Monte Cristo I project in same county, same technology. Tax abatement agreement confirms Monte Cristo II LLC is the legal entity. Terra-Gen (jointly owned by Masdar and Igneo Infrastructure Partners) is the operating parent.
Status: LBNL shows 'Active' with IA executed 2025-12-19. Tax abatement agreement dated July 2025 confirms local permitting progress. No press releases announce construction start or financing close, unlike sister project Monte Cristo I which went operational Nov 2025.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Monte Cristo 2 Wind project is a proposed 233.9 MW wind generation facility located in Hidalgo County, Texas. The project, being developed by Terra-Gen, is currently active in the ERCOT interconnection queue as entry ERCOT-19INR0055, with a queue entry date of April 11, 2017. The proposed commercial operation date is December 31, 2028, and the project's interconnection status is currently in the Facility Study phase.
The Monte Cristo 2 Wind project has been the subject of recent news coverage, with eight articles focusing on deals and industry developments related to the project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hidalgo
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Monte Cristo Windpower II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8574 Pomelo 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ANEM_ESS_RN
- POI Substation
- Pomelo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14
View all articlesMax 4 Wind
Data tables and metrics from the InfraSure database.
FPL Energy Oliver Wind II LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Wind queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
FPL Energy Oliver Wind I LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.