Briefing/projectactive
Mesquite Solar 6 is a 309 MW Solar+Battery project in Arizona, currently active.
The reported queue phase is Cluster 15. Proposed COD is 2028-04-30.
- Queue ID
- CAISO-2279
- Location
- Maricopa, Arizona
- Technology
- Solar+Battery
- Market / region
- CAISO
- Point of interconnection
- HASSAYAMPA 500 kV
What stands out
1
Mesquite Solar 6 is a 309 MW Solar+Battery project in Arizona with status active.
2
The reported queue phase is Cluster 15; proposed COD is 2028-04-30.
Market and operating context
- Queue date
- 2023-04-17
- Proposed COD
- 2028-04-30
- IA status
- Not Started
- Study phase
- Cluster 15
- Service type
- ERIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.