Briefing on Merope BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
402 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-03-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Merope BESS is a 402 MW Battery project in Texas, currently active.

BRP Merope BESS LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-03-01.

Queue ID
ERCOT-24INR0157
Location
Comanche, Texas
Technology
Battery
Developer
BRP Merope BESS LLC
Market / region
ERCOT
Point of interconnection
345 kV Corn Trail Switch Substation (#11441)

What stands out

1

Merope BESS is a 402 MW Battery project in Texas with status active.

2

BRP Merope BESS LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-03-01.

Market and operating context

Queue date
2021-12-20
Proposed COD
2028-03-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Merope BESS — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0157
LocationComanche, Texas
TechnologyBattery
DeveloperBRP Merope BESS LLC
Market / regionERCOT
Point of interconnection345 kV Corn Trail Switch Substation (#11441)
Queue date2021-12-20
Proposed COD2028-03-01