Merom Station is a 530 MW Battery project in Indiana, currently active.
Hallador Power is the reported developer. The reported queue phase is In Progress (unknown study). Proposed COD is 2028-11-01.
- Queue ID
- MISO-E0054
- Location
- Sullivan, Indiana
- Technology
- Battery
- Developer
- Hallador Power
- Market / region
- MISO
- Point of interconnection
- Merom Substation
What stands out
1
Merom Station is a 530 MW Battery project in Indiana with status active.
2
Hallador Power is the reported developer.
3
The reported queue phase is In Progress (unknown study); proposed COD is 2028-11-01.
Market and operating context
- Queue date
- 2025-11-04
- Proposed COD
- 2028-11-01
- IA status
- In Progress (unknown study)
- Study phase
- In Progress (unknown study)
- Service type
- NRIS
Why it matters