Briefing on Meriwether Panther Solar

Entity Briefing
Generated Oct 13, 2026·Dataset freshness not reported
125 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
Southeast
Market / region
2026-12-31
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Meriwether Panther Solar is a 125 MW Solar+Battery project in Georgia, currently active.

The reported queue phase is Facility Study. Proposed COD is 2026-12-31.

Queue ID
GTC-GI-161
Location
Meriwether, Georgia
Technology
Solar+Battery
Market / region
Southeast
Point of interconnection
GTC 115 kV substation on Rocky Mount Rd

What stands out

1

Meriwether Panther Solar is a 125 MW Solar+Battery project in Georgia with status active.

2

The reported queue phase is Facility Study; proposed COD is 2026-12-31.

Market and operating context

Queue date
2022-01-28
Proposed COD
2026-12-31
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Meriwether Panther Solar — verified asset snapshot

FieldValue
Queue IDGTC-GI-161
LocationMeriwether, Georgia
TechnologySolar+Battery
Market / regionSoutheast
Point of interconnectionGTC 115 kV substation on Rocky Mount Rd
Queue date2022-01-28
Proposed COD2026-12-31
IA statusFacility Study