Briefing on Meitner Solar

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
703 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2027-12-20
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Meitner Solar is a 703 MW Solar project in Texas, currently active.

Intersect Power is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-12-20.

Queue ID
ERCOT-25INR0080
Location
Gray, Texas
Technology
Solar
Developer
Intersect Power
Market / region
ERCOT
Point of interconnection
345 kV Gray (Bus# 79000)

What stands out

1

Meitner Solar is a 703 MW Solar project in Texas with status active.

2

Intersect Power is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2027-12-20.

4

Latest linked story: “Intersect Power’s Tax Abatement Request Approved by County Commissioner’s Court” (Pampa News, 2024-01-15).

Market and operating context

Queue date
2022-08-05
Proposed COD
2027-12-20
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Meitner Solar — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0080
LocationGray, Texas
TechnologySolar
DeveloperIntersect Power
Market / regionERCOT
Point of interconnection345 kV Gray (Bus# 79000)
Queue date2022-08-05
Proposed COD2027-12-20