Briefing/projectactive
Masava Storage is a 257 MW Battery project in Texas, currently active.
Savannah Oaks Solar Project, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-09-30.
- Queue ID
- ERCOT-25INR0176
- Location
- Madison, Texas
- Technology
- Battery
- Developer
- Savannah Oaks Solar Project, LLC
- Market / region
- ERCOT
- Point of interconnection
- tap 345 kV 46020 Limestone Plant - 967 Gibbons Creek ckt 18
What stands out
1
Masava Storage is a 257 MW Battery project in Texas with status active.
2
Savannah Oaks Solar Project, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2028-09-30.
Market and operating context
- Queue date
- 2022-09-02
- Proposed COD
- 2028-09-30
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.