Briefing/projectactive
Maple Hill-Fiddlers 1 SP (Bear Rock) is a 50 MW Solar project in Pennsylvania, currently active.
OPC Energy is the reported developer. The reported queue phase is TC1. Proposed COD is 2021-09-01.
- Queue ID
- PJM-AF2-050
- Location
- Cambria, Pennsylvania
- Technology
- Solar
- Developer
- OPC Energy
- Market / region
- PJM
- Point of interconnection
- Bear Rock-Johnstown 230 kV
What stands out
1
Maple Hill-Fiddlers 1 SP (Bear Rock) is a 50 MW Solar project in Pennsylvania with status active.
2
OPC Energy is the reported developer.
3
The reported queue phase is TC1; proposed COD is 2021-09-01.
Market and operating context
- Queue date
- 2019-12-23
- Proposed COD
- 2021-09-01
- IA status
- System Impact Study
- Study phase
- TC1
- Service type
- NRIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.